Data Center Design to Operations: The Data Center Life Cycle
Understanding the intricacies of the data center life cycle is crucial for stakeholders involved in building a data center, from initial planning and data center design to ongoing operations.
This article will explore the various phases of the data center life cycle, emphasizing the importance of meticulous planning, design, construction, and continuous assessment to optimize performance and meet the dynamic demands of modern enterprises.
1. Data Center Planning
Phase length: a few weeks to a few months, depending on the scale of the project
Phase output: a validated system concept (high level description of the system)
Despite usually being the shortest and least expensive stage of the data center life cycle, the planning phase is critical because of the impact it has on the overall cost and capabilities of the data center. Failure to plan a data center project properly can result in rework and costly delays as a result.
“This planning phase should determine the key project parameters of the physical system to be created (system concept), site selection, and the project process that will determine them.” Schneider Electric – Data Center Science Center
To avoid problems later on in the process, it is recommended to use a formal, standardized process.
Data center site selection
Once a system concept has been established, site evaluation can begin. If a site is selected too early, it may end up not meeting the design requirements. There are many factors that go into site selection for a data center, including climate, connectivity, and capacity for expansion.
2. Data Center Design
Phase length: between four and ten weeks depending on whether there’s a bidding element included
Phase output: site-specific schematics, detailed construction documents, and a project plan
The design phase of data center project transforms the system concept from the planning phase into site-specific schematics, detailed drawings, and specifications. During this phase, these documents are reviewed and approved by engineers and relevant authorities before construction contractors are appointed.
Parties involved in this detailed design phase include the project owner, the data center architect, MEP engineers, structural and civil engineers, IT consultants, energy consultants, commissioning agents and facility operators.
“Unfortunately, it is common to go through multiple design iterations as requirements, preferences, and constraints change or surprises occur. If the early planning phase is managed properly as described above, these costly, time-consuming iterations will be minimized.” Schneider Electric – Data Center Science Center
Before starting the build phase, the construction team will create a detailed project plan, identifying critical path items and developing a commissioning plan, budget, billing plan, and schedule. At this stage, close collaboration with the design team is really important to ensure that the finalized design and construction documents align with the project’s plans, schedules, and budgets.
Looking for a data center design role?
3. Data Center Building
Phase length: 6 months to 3 years
Phase output: Completed building with certification of completion
During the building phase, construction begins in accordance with the detailed documents produced in the planning and design phases. Team members focus on their respective disciplines such as civil construction, QA/QC, mechanical, electrical, equipment integration and so on.
The building phase can be considered complete when quality assurance has confirmed and a final certification of completion is issued. The commissioning test results must have been received and the owner should issue a formal letter of acceptance of project.
Data Center Commissioning
“Commissioning (Cx) is defined as a reliability science that documents and validates the result of a data center’s design and build processes. This is very different from typical “start-up” services where equipment vendors simply install, configure, power-up devices, and then provide the contractor with a certificate of completion for each individual device.” Schneider Electric – Data Center Science Center
Not only is commissioning recommended for new data center projects, but also retrofit projects where there have been significant changes made to the overall system. Commissioning agents should be involved in the project from an early stage so that any points of failure can be identified early on in the process.
After commissioning tests have been passed, the project can be handed over to the facilities operations team.
Looking for a data center commissioning role?
4. Data Center Operations
Phase length: 10 to 20 years
Phase output: Continuously house, power, cool, and secure IT servers, storage, and networking gear
The longest phase of a data center project is the operations phase. During this phase, the physical infrastructure must continuously function despite the equipment aging and fluctuations in IT and business demands.
Looking for a data center operations role?
5. Data Center Assessment
Phase length: monthly measurements throughout the operations phase
Phase output: knowledge of whether the data center is operating well and opportunity to address any issues
Regularly assessing the performance of a data center is an important element of an effective operations and maintenance program.
According to Schneider Electric, an effective regular assessment should include assessing the:
- Degree to which the design intent and facility objectives are being met by the current infrastructure in operation
- Energy efficiency of physical infrastructure in supporting IT
- General health and current risk profile of the physical infrastructure
- Current power, cooling, and space capacities and use trends
- Effectiveness and experience levels of personnel
- Facility operations and maintenance program maturity and effectiveness
A number of metrics should be measured and tracked against a target value and ‘acceptable’ levels. Any deviations from the accepted values should be addressed.
Subscribe to the DC Digest
Your fortnightly update on everything going on in the data centre industry, all in one place.
DC Digest
Recent data centre news:
- Independent Power Transmission Operator and Serverfarm Join Forces to Spearhead Hyperscale Data Center Development and Operations in Greece
- Weekly Data Centre Digest – 13th December 2024
- Wonder Valley: The Largest AI Compute Data Centre Park On Earth
- AVK and Rolls-Royce Reinforce Commitment to Net-Zero, with Record-Breaking Year for HVO-Powered Generator Sales
- Weekly Data Centre Digest – 6th December 2024
Inside Data Centre Podcast
The journey of building a data center is complex and multifaceted, encompassing critical stages from planning and design to operations and assessment. Each phase of the data center life cycle requires careful consideration and execution to ensure that the final infrastructure aligns with organizational goals and technological needs.
By adhering to established best practices in data center design and continuously evaluating performance throughout the operations phase, organizations can enhance the reliability, efficiency, and longevity of their data centers. As technology continues to advance, embracing a proactive approach to the data center life cycle will be vital for staying competitive in an increasingly data-driven landscape.
Other insights
-
CV Writing and Interview Skills with Ark Data Centres at The Bicester School
We co-hosted a Digital Futures workshop at The Bicester School with ARK Data Centres. Together, we ran sessions for Year 12 on CV writing and interview techniques.
-
Empowering Future Engineers: UTC Reading’s Community Project Day
We recently had the opportunity to volunteer as mentors at UTC Reading’s Community Project Day. Partnering with the Amuka Foundation, the event challenged students to develop real-world solutions to improve infrastructure and education at Loruko Primary School, a rural school in Kenya facing significant challenges.
-
Mentoring Tomorrow’s Data Centre Talent: Digital Futures Programme at UTC Oxfordshire
Recently, we had the privilege of participating in a Digital Futures Programme Challenge Day at UTC Oxfordshire, where Year 10 and Year 12 students took on the ambitious task of designing a fully operational data centre.
-
Fixing the Data Centre Talent Shortage Through Partnerships with Schools
A group of secondary schools are working in a new, innovative way with forward-thinking digital infrastructure companies to upskilling students in digital and technical skills, after a report calls on the government to act urgently to address a growing digital skills gap that, if left unchecked, could lose the economy billions.
-
Digital Futures Programme hosts Thrilling Sustainability Challenge Day with KAO Data
Students at UTC Heathrow were immersed in an exciting and educational day of challenges focused on sustainability in data centres, hosted by KAO Data and supported by VIRTUS, Vertiv, JLL, Cyrus One, LMG, AWS, ARK, and others.
-
Increasing Apprenticeship Opportunities in the Data Centre Industry: Our Platinum Membership in The 5% Club
We’re thrilled that we’ve been awarded Platinum accredited membership as part of The 5% Club’s esteemed 2024-25 Employer Audit Scheme.